Current Projects
HATFIELD RANCH ON BROADWAY
GENERAL CONTRACTOR/OWNER:
NEWCASTLE DEVELOPMENT
6628 EAST BASELINE ROAD, SUITE 102
MESA, ARIZONA 85206
CONTRACT AMOUNT:
$629,460.00
PERCENT COMPLETE:
42%
PROJECTED COMPLETION DATE:
JULY 2021
EARTH MOVED:
25,000 CUBIC YARDS
ASPHALT INSTALLED:
2,000 TONS
BOEING ADVANCED FABRICATION CENTER
GENERAL CONTRACTOR/OWNER:
BE&K BUILDING GROUP, LLC
201 EAST MCBEE AVENUE, SUITE 400
GREENVILLE, SOUTH CAROLINA 29601
CONTRACT AMOUNT:
$1,853,033.00
PERCENT COMPLETE:
55%
PROJECTED COMPLETION DATE:
SEPTEMBER 2021
EARTH MOVED:
60,000 CUBIC YARDS
ASPHALT INSTALLED:
8,500 TONS
GILBERT CROSSROADS PHASE 2
GENERAL CONTRACTOR/OWNER:
WILLMENG CONSTRUCTION, INC
2048 NORTH 44TH STREET, SUITE 200
PHOENIX, ARIZONA 85008
CONTRACT AMOUNT:
$614,149.00
PERCENT COMPLETE:
59%
PROJECTED COMPLETION DATE:
JULY 2021
EARTH MOVED:
50,000 CUBIC YARDS
ASPHALT INSTALLED:
3,000 TONS
PV 303 XPO LOGISTICS & OFFSITES
GENERAL CONTRACTOR/OWNER:
STEVENS-LEINWEBER CONSTRUCTION, INC
730 EAST HIGHLAND AVENUE
PHOENIX, ARIZONA 85014
CONTRACT AMOUNT:
$2,786,905.00
PERCENT COMPLETE:
50%
PROJECTED COMPLETION DATE:
AUGUST 2021
EARTH MOVED:
250,000 CUBIC YARDS
ASPHALT INSTALLED:
8,000 TONS
COMMERCE 303 DISTRIBUTION FACILITY
GENERAL CONTRACTOR/OWNER:
LAYTON CONSTRUCTION COMPANY, LLC
2355 EAST CAMELBACK ROAD, SUITE 800
PHOENIX, ARIZONA 85016
CONTRACT AMOUNT:
$2,702,901.00
PERCENT COMPLETE:
2%
PROJECTED COMPLETION DATE:
AUGUST 2021
EARTH MOVED:
275,000 CUBIC YARDS
ASPHALT INSTALLED:
6,000 TONS
PEPSI CO TCP BUILDING E
GENERAL CONTRACTOR/OWNER:
STEVENS-LEINWEBER CONSTRUCTION, INC
730 EAST HIGHLAND AVENUE
PHOENIX, ARIZONA 85014
CONTRACT AMOUNT:
$1,225,307.00
PERCENT COMPLETE:
79%
PROJECTED COMPLETION DATE:
JULY 2021
EARTH MOVED:
225,000 CUBIC YARDS
ASPHALT INSTALLED:
ALL PCCP
SARIVAL LOGISTICSS CENTER
GENERAL CONTRACTOR/OWNER:
LAYTON CONSTRUCTION COMPANY, LLC
2355 EAST CAMELBACK ROAD, SUITE 800
PHOENIX, ARIZONA 85016
CONTRACT AMOUNT:
$4,257,674.00
PERCENT COMPLETE:
0%
PROJECTED COMPLETION DATE:
APRIL 2022
EARTH MOVED:
800,000 CUBIC YARDS
ASPHALT INSTALLED:
16,000 TONS
LAKIN INDUSTRIAL PARK BLDG A
GENERAL CONTRACTOR/OWNER:
LAYTON CONSTRUCTION COMPANY, LLC
2355 EAST CAMELBACK ROAD, SUITE 800
PHOENIX, ARIZONA 85016
CONTRACT AMOUNT:
$2,929,391.00
PERCENT COMPLETE:
65%
PROJECTED COMPLETION DATE:
OCTOBER 2021
EARTH MOVED:
400,000 CUBIC YARDS
ASPHALT INSTALLED:
ALL PCCP
ELLIOT 202
GENERAL CONTRACTOR/OWNER:
WILLMENG CONSTRUCTION, INC
2048 NORTH 44TH STREET, SUITE 200
PHOENIX, ARIZONA 85008
CONTRACT AMOUNT:
$2,659,165.00
PERCENT COMPLETE:
53%
PROJECTED COMPLETION DATE:
OCTOBER 2021
EARTH MOVED:
300,000 CUBIC YARDS
ASPHALT INSTALLED:
4,000 TONS
LANDING 4 ELECTRA MECCANICA
GENERAL CONTRACTOR/OWNER:
WILLMENG CONSTRUCTION, INC
2048 NORTH 44TH STREET, SUITE 200
PHOENIX, ARIZONA 85008
CONTRACT AMOUNT:
$795,732.00
PERCENT COMPLETE:
32%
PROJECTED COMPLETION DATE:
DECEMBER 2021
EARTH MOVED:
90,000 CUBIC YARDS
ASPHALT INSTALLED:
1,000 TONS
NORTHRUP GRUMMAN EXPANSION
GENERAL CONTRACTOR/OWNER:
WILLMENG CONSTRUCTION, INC
2048 NORTH 44TH STREET, SUITE 200
PHOENIX, ARIZONA 85008
CONTRACT AMOUNT:
$780,868.00
PERCENT COMPLETE:
55%
PROJECTED COMPLETION DATE:
JULY 2021
EARTH MOVED:
45,000 CUBIC YARDS
ASPHALT INSTALLED:
2,000 TONS
LAGERHAUS - RED BULL WAREHOUSE
GENERAL CONTRACTOR/OWNER:
LAYTON CONSTRUCTION COMPANY, LLC
2355 EAST CAMELBACK ROAD, SUITE 800
PHOENIX, ARIZONA 85016
CONTRACT AMOUNT:
$1,777,409.00
PERCENT COMPLETE:
87%
PROJECTED COMPLETION DATE:
JUNE 2021
EARTH MOVED:
245,000 CUBIC YARDS
ASPHALT INSTALLED:
ALL PCCP
KENTWOOD 303
GENERAL CONTRACTOR/OWNER:
WILLMENG CONSTRUCTION, INC
2048 NORTH 44TH STREET, SUITE 200
PHOENIX, ARIZONA 85008
CONTRACT AMOUNT:
$1,581,261.00
PERCENT COMPLETE:
19%
PROJECTED COMPLETION DATE:
NOVEMBER 2021
EARTH MOVED:
100,000 CUBIC YARDS
ASPHALT INSTALLED:
8,500 TONS
PEBBLE CREEK 303 BLDG C-19
GENERAL CONTRACTOR/OWNER:
STEVENS-LEINWEBER CONSTRUCTION, INC
730 EAST HIGHLAND AVENUE
PHOENIX, ARIZONA 85014
CONTRACT AMOUNT:
$1,257,484.00
PERCENT COMPLETE:
82%
PROJECTED COMPLETION DATE:
JUNE 2021
EARTH MOVED:
350,000 CUBIC YARDS
ASPHALT INSTALLED:
ALL PCCP
AIRGATE 1
GENERAL CONTRACTOR/OWNER:
WILLMENG CONSTRUCTION, INC
2048 NORTH 44TH STREET, SUITE 200
PHOENIX, ARIZONA 85008
CONTRACT AMOUNT:
$949,078.00
PERCENT COMPLETE:
20%
PROJECTED COMPLETION DATE:
JULY 2021
EARTH MOVED:
25,000 CUBIC YARDS
ASPHALT INSTALLED:
4,000 TONS
MESA CEMETERY NORTH EXPANSION
GENERAL CONTRACTOR/OWNER:
LOW MOUNTAIN CONSTRUCTION, INC
4105 NORTH 20TH STREET, SUITE 205
PHOENIX, ARIZONA 85016
CONTRACT AMOUNT:
$182,961.46
PERCENT COMPLETE:
0%
PROJECTED COMPLETION DATE:
SEPTEMBER 2021
EARTH MOVED:
25,000 CUBIC YARDS
ASPHALT INSTALLED:
300 TONS
ZIPRECRUITER - 1ST & 2ND FLOOR
GENERAL CONTRACTOR/OWNER:
WILLMENG CONSTRUCTION, INC
2048 NORTH 44TH STREET, SUITE 200
PHOENIX, ARIZONA 85008
CONTRACT AMOUNT:
$14,870.44
PERCENT COMPLETE:
100%
PROJECTED COMPLETION DATE:
JUNE 2021
EARTH MOVED:
N/A
ASPHALT INSTALLED:
N/A
PARK LUCERO EAST
GENERAL CONTRACTOR/OWNER:
WILLMENG CONSTRUCTION, INC
2048 NORTH 44TH STREET, SUITE 200
PHOENIX, ARIZONA 85008
CONTRACT AMOUNT:
$3,757,878.00
PERCENT COMPLETE:
18%
PROJECTED COMPLETION DATE:
NOVEMBER 2021
EARTH MOVED:
350,000 CUBIC YARDS
ASPHALT INSTALLED:
5,500 TONS
COPPER SUN - ADDITIONAL LOTS
GENERAL CONTRACTOR/OWNER:
WILLMENG CONSTRUCTION, INC
2048 NORTH 44TH STREET, SUITE 200
PHOENIX, ARIZONA 85008
CONTRACT AMOUNT:
$217,599.00
PERCENT COMPLETE:
0%
PROJECTED COMPLETION DATE:
JULY 2021
EARTH MOVED:
23 LOT SUBDIVISION
ASPHALT INSTALLED:
400 TONS